OPW – 204th and Cumberland Signal Modifications

  • Construction started in April 2016 with Swain Construction as the Prime Contractor for the City of Omaha.

  • Major work included the installation modification of the existing traffic signal intersection by installing a new 70’ mast arm with signals and signage, a new 42” diameter x 17’ deep foundation, new IMSA signal wiring, radar detection, and temporary signals during construction phasing. All work was completed under an active roadway with vehicular and pedestrian traffic